Works update at Middleton Field

With the recent fine Spring weather in Daylesford Stage 3 works are progressing well at Middleton Field. Civil contractor Winslow have also commenced on the site of The Village to enable the start of construction of the first sustainable townhouses designed by Breathe.

Image from a recent site meeting for Stage 3 works at Middleton Field including Catherine from Hygge Property, Mark from Axiom Engineering, and Lachlan and Shane from Winslow Construction.

Stage 3 works and settlement update

Kerb and channel installation forming part of the road network is now complete with footpath preparation underway.

In the coming weeks, asphalt will be laid following the installation of Powercor electrical cables and NBN infrastructure.

Settlement for homesites in Stage 3 is anticipated this Spring.

This timeframe remains indicative only based on current information relating to completion of civil works and receipt of approvals from relevant authorities, with settlement dependent on receiving a Statement of Compliance from Hepburn Shire Council.

As the date for settlement approaches, the project team will be in regular contact with the purchasers in Stage 3 with timing updates.

The short video shows civil construction works underway for Stage 3 including creation of the new road network and homesites in the Vista Collection with the Wombat Hill Botanic Gardens as the backdrop.

 
Laura van Dyk